Assigning severity to incidents, deciding when and whom to page, and moving an issue up defined escalation paths. Covers severity matrices and objective impact criteria (customer impact, scope, data loss, regulatory and financial exposure, multi-tenant and multi-region cases), major-incident declaration thresholds, triage and prioritization across concurrent incidents, escalation criteria and timing, executive and vendor escalation, and calibrating or auditing severity definitions over time, including severity metrics, rolling out threshold changes, centralized versus team-owned classification, training responders to classify, reducing false-positive top-severity pages, and automated or learned severity classification. Applied to services, data and reporting platforms, and machine-learning systems. The routing and prioritization discipline at the front of the incident lifecycle. Excludes running the response once staffed, on-call rotation and runbook design, incident status communication, and SLO definition.
Which signals should drive an incident severity decision, and which charts or indicators would you look at first to judge user impact? How do you tell a real customer-facing problem from a noisy internal metric?
Sample Answer
The idea in plain words
Severity should be decided from what users experience and how many of them, not from how alarming an internal graph looks. So the first charts are the ones that measure the user's outcome (do requests succeed, how fast, is traffic what it should be), split by who is affected. Internal metrics such as CPU, queue depth or a single host's errors are clues to a cause; they become evidence of severity only when a user-facing signal moves with them.
Terms used below. Severity (SEV) is the tier of seriousness that decides who is paged. SLI (service-level indicator) is a measured quality such as the share of requests that succeed. Error rate is failed requests divided by all requests. p99 latency is the response time that 99% of requests beat. Edge is the entry layer (load balancers, CDN) where user requests first arrive. Saturation is how full a resource is. Synthetic probe is a scripted test that exercises a user journey from outside, for example logging in and paying every minute.
Which signals drive the decision
Think of three questions: how bad is it for those affected, how many are affected, and is it getting worse. Four signals answer most of it, matching the widely used "four golden signals" of latency, traffic, errors and saturation:
- Errors on key user journeys. Success rate of login, search, checkout, measured at the edge (the entry point that user requests hit first) or by probes. Look at the ratio, not the raw count.
- Latency percentiles. p50 and p99, with successful and failed requests separated, because fast failures can make average latency look good.
- Traffic compared with expectation. Requests per second against the same hour last week. A drop can mean users cannot reach you, which no error counter will show.
- Saturation (how full a resource is). This tells you whether things will get worse, so it informs the trend, not the severity today.
Then add two outside-in signals that the system cannot fake: support tickets and social mentions per hour, and client-side error reports from apps and browsers.
What to look at first, in order
- The overview of the main user journeys' success rate over the last hour. Is any below its target?
- The same chart split by region, customer, app version and endpoint. This gives scope: all users, one region, one large customer?
- Latency p50 against p99, and traffic against last week.
- Whether a second, independent source agrees (probe, client reports, tickets).
- Only then the internal causes: saturation, dependency errors, recent deploys.
Real customer problem or noisy internal metric?
Run each alert through five tests:
- Is it on the user path? A metric that no user request passes through cannot hurt users directly.
- Is a second source corroborating it? One alert alone is a lead; two independent sources is a problem.
- Is it a deviation from its own normal? Compare with the same time last week, since some jobs are busy at the same hours every week.
- Is it sustained and based on enough volume? Two failures out of 20 requests is 10% and tells you nothing. Require a minimum request count and persistence across a few minutes.
- Does it have a ratio against traffic? A raw error count rises whenever traffic rises.
Worked example (hypothetical numbers)
Two alerts fire at the same moment.
| Signal | Value | Normal | Reading |
|---|---|---|---|
| Worker pool CPU | 92% | 60 to 70% | Internal clue. On its own it shows no user harm: p99 latency is unchanged and the checkout failures in the next row are confined to one region, so this pool is not shown to cause them. Ticket it, watch the saturation trend, and promote it only if it turns out to share that region or onset time with the failures. |
| Checkout success rate (global) | 96.8% | 99.95% | User-facing. Error rate is 100−96.8=3.2%. |
Scope: the split shows all failures in one region that carries about one third of traffic. If that region caused the whole 3.2%, its own error rate is about 3.2×3=9.6% (assuming traffic is evenly one third and nothing else fails). Probes in that region agree and support tickets mention payment errors. Impact is large for one third of users and getting worse, so declare SEV1 for that region using the scale in the next section, and keep the CPU alert as a lower-priority lead. The same CPU alert with flat checkout success would have stayed a ticket.
A severity yardstick to apply it to
The scale below is an assumed example; each organisation sets its own. A core journey is one the business cannot do without, such as login or checkout.
| Level | Meaning (assumed) |
|---|---|
| SEV1 | A core journey fails for 5% or more of requests in a segment holding at least 10% of users, or is fully down. Everyone responds now. |
| SEV2 | A core journey fails for 1% to under 5% of requests in such a segment, or 5% or more in a smaller segment. |
| SEV3 | Below those lines, or only internal signals. A ticket. |
Apply it to the example: globally the error rate is 3.2%, which alone would read as SEV2. The split shows the failing region has about 9.6% errors (above 5%) and holds one third of users (above 10%), so the region meets the SEV1 line. This is the reason to split every chart by region and customer before choosing a level.
Reading latency percentiles: if p50 (the median, half of requests are faster) is 180 ms and p99 is 4,200 ms, then most users are fine but 1 request in 100 waits over four seconds; a p50 that is unchanged with a rising p99 points at a bad tail, not a general slowdown.
Pitfalls
- Treating every threshold breach as an incident and training people to ignore pages.
- Looking only at averages, which hide a bad tail.
- Looking only at global numbers, which dilute a failing region or a single big customer.
- Trusting a dashboard that depends on the failing system.
During the first 15 minutes after receiving a page for a service degradation, list the top eight clarifying questions you should ask to triage effectively. For each question, explain why it matters and how your line of questioning would differ if the pager says 'service degraded' versus 'service down'.
Sample Answer
The idea in plain words
Triage means sizing a problem quickly so the right response starts. When a page (an automated alert to your phone) says "service degraded" or "service down", you know almost nothing yet. The first 15 minutes are for turning that one line into five facts: what is wrong, who is hurt, whether it is getting worse, what changed, and whether a safe fix exists now. The eight questions below are asked in this order because each answer changes how you ask the next one. "Degraded" means the service still answers but slowly, with more errors, or for only some users. "Down" means it does not serve its purpose at all. The difference changes your urgency, your mitigation menu and how soon you call for help.
If time is short, the four that matter most are question 2 (who is hurt), question 3 (is it getting worse), question 4 (what changed) and question 6 (is there a safe fast mitigation); the other four refine the picture or protect against mistakes.
The eight questions
| # | Question | Why it matters | If the page says "degraded" | If the page says "down" |
|---|---|---|---|---|
| 1 | What exactly fired, and is it still firing? | An alert is a measurement crossing a threshold; it can be a false alarm, a blip, or a monitor fault | Read the metric and threshold: is it a slow trend (latency creeping up) or a step? | Check the alert is not the monitor itself failing: can you reach the service by hand (a test request)? |
| 2 | Who is affected, and how badly? | Impact decides severity and whom to call | What fraction of requests are slow or failing, and for which users, regions or tenants (separate customer accounts sharing the service)? | Is every user locked out, or only one region or tenant? "Down" for one customer is a different incident from "down" for all |
| 3 | Is it getting worse, stable or recovering? | A fault that grows needs action in minutes; a recovering one needs watching | Plot the last 30 minutes: a rising error rate or queue is the trigger to act now | Check whether it is a cliff (sudden) or a slide, and whether traffic is retrying and making it worse |
| 4 | What changed recently? | Most incidents follow a change: deploy, configuration, flag, certificate, traffic | Look at the change log for the last few hours; a deploy near the start time is the first suspect | Same, plus infrastructure events (an instance replaced, a certificate expiry, a quota hit) |
| 5 | Is it one component or a chain? | Dependencies fail too, and knowing which dependency saves time | Compare latency (how long requests take), errors (the share that fail), traffic (how many arrive) and saturation (how full the busiest resource is, such as CPU, memory, connections or queue length) on this service and its dependencies; these are the four "golden signals" | Check the dependencies and the provider's status pages; a hard down is often a dependency, network or credential failure |
| 6 | Is there a safe, fast mitigation? | Restoring service beats explaining it; mitigation is the temporary relief, the fix comes later | Options: scale up, shed load (deliberately refuse or delay some low-priority requests so the rest succeed), turn off a heavy feature with its feature flag (a switch that disables code without a deploy), restart one bad node | Options: roll back the last change, fail over (switch traffic to a standby region or a replica, a live copy of the service or database), restore from the last good version |
| 7 | Is data or security at risk? | Data loss or exposure moves the incident into a different category with legal clocks | Are results wrong rather than slow (stale, duplicated, partial)? | Is the service down because someone shut it off on purpose, or could it be an attack? |
| 8 | Do I need help, and what severity do I declare? | Waiting alone is the commonest mistake; severity triggers the right people | Declare a level from the impact table; warn the owning team if the trend is rising | Down on a core journey normally means declaring the top severity immediately and paging backup, without waiting to confirm cause |
A 15-minute order of play
| Minutes | Do | Questions |
|---|---|---|
| 0 to 2 | Acknowledge the page (so the system stops re-paging), open the dashboard, make one hand-made test request (a synthetic check: a request you send yourself to see what a user would see) | 1 |
| 2 to 5 | Size impact: how many users, which part, trend over the last 30 minutes | 2, 3 |
| 5 to 10 | Check recent changes and dependencies; decide whether a rollback or traffic shift is cheap and safe | 4, 5, 6 |
| 10 to 15 | Decide severity at the latest here (declare it earlier whenever the impact is already clear, as in the example below), call for help or declare an incident, and set the time of your next check-in; check for data risk before touching anything irreversible | 7, 8 |
If you are near minute 10 without a mitigation and the impact is rising, call for help at that point; do not spend all 15 minutes alone.
Worked example (hypothetical)
Page: "checkout latency degraded". 0 to 2: alert shows p95 latency (the time within which 95% of requests complete) at 3.1 seconds against a 2 second limit. Test request is slow but succeeds. 2 to 5: about 15% of requests are over the limit; trend rising for 20 minutes; only the EU region. 5 to 10: a configuration change went to the EU region 25 minutes ago. Rolling that change back is safe and quick. 10 to 15: after rollback p95 returns to 1.2 seconds; a SEV2 was declared at minute 8 because the trend was rising, then downgraded after recovery; the next check-in was set 15 minutes later.
The same alert worded "checkout down" would change the order: question 2 (who is hit) and 6 (rollback or failover) come first, severity is declared at minute 2 instead of minute 8, and backup is paged immediately.
Judgment
The minute marks are deadlines, not a script: severity is declared the moment impact is clear (minute 8 in the example, minute 2 for a hard down), and a rollback is not held back for the minute 10 to 15 box. I would not try to answer all eight questions before acting: if question 4 shows a deploy right at the start and a rollback is safe, the rollback goes ahead at minute 5, and the rest are answered while it runs. What would change this: if question 7 raises any data or security risk, slow down and involve the owner before changing anything irreversible.
Common mistakes: staying silent for 15 minutes; starting by reading logs instead of sizing impact; treating "degraded" as "not urgent" when the trend is rising; changing several things at once so the effect cannot be judged.
What does incident severity mean, and how does it differ from priority? Give concrete examples of each, and define a set of severity levels with objective criteria for each.
Sample Answer
The idea in plain words
An incident is an unplanned event that degrades or threatens a service. Severity measures how bad the impact of that incident is: how many customers, how much of the product, whether data or money is at risk. Priority measures how urgently, and in what order, the work should be scheduled once you also count deadlines, available people, cost of delay (the harm or lost value that builds up for every extra hour the problem stays unfixed) and how cheap the fix is. Severity answers "how bad is this?" and priority answers "what do we work on first?". They usually move together, but they are separate axes, and the cases where they disagree are the ones that show you understand the difference.
Concrete examples of each
SEV is short for severity: SEV1 is the most severe level and SEV4 the least, so the number is a label for a level, not a count of anything. The levels are defined in the next section; the table below already names the level each example lands in.
| Situation | Severity (impact) | Priority (urgency of work) | Why they differ |
|---|---|---|---|
| Checkout fails for 12% of requests | High (SEV2) | Top | They agree: big impact, nothing else matters more |
| A sale ended at midnight but the homepage banner still advertises it, support chats are filling up, and the fix is a one-line config change | Low, SEV4 (no function is broken) | High (fix within the hour) | Cheap fix plus customer confusion and possible refund disputes |
| A quarterly export used by three internal staff fails completely | Minor, SEV3 (the feature is entirely unusable, but for few people, with a workaround) | Low (schedule for the next sprint) | Few users, a workaround exists, no deadline for a few weeks |
| A typo in a footer link label | Low (SEV4) | Low | They agree again |
Defining severity levels with objective criteria
A criterion is objective when two different on-call engineers (the people who are paged when something breaks) looking at the same dashboard would put the incident in the same level. That means numbers and observable facts, not words like "serious". Good rules for the table:
- Base levels on impact (what customers experience), never on cause or on how hard the fix is.
- Use thresholds with a time window so a 30-second blip does not count.
- Evaluate from the top level down and take the first level whose condition is met.
- Treat data loss and security exposure as top-level regardless of duration or percentage.
Assumptions for this example (stated, not universal): a customer-facing web product with a "core journey" and non-core features. A core journey is a path a customer must be able to complete for the product to deliver its value, here sign-in and checkout; every other feature is non-core.
| Level | Objective criteria (any one is enough) | Typical example |
|---|---|---|
| SEV1 (critical) | Core journey failing for at least 50% of requests for 5 minutes or more; or confirmed loss or corruption of customer data; or confirmed unauthorised access to customer data | Sign-in down for most users |
| SEV2 (major) | Core journey failing for at least 5% and under 50% of requests for 5 minutes or more; or a major feature unavailable with no workaround | Checkout failing for a tenth of requests |
| SEV3 (minor) | Core journey failing for under 5% of requests, or a non-core feature degraded or unavailable, and a workaround exists | A report export is down |
| SEV4 (low) | Cosmetic or single-user issue, no impact on function | Misaligned button |
The boundaries are written with "at least" and "under" so that exactly 5% and exactly 50% each land in exactly one level.
Worked example: same table, severity versus priority
| Incident | Check against the table | Severity | Priority |
|---|---|---|---|
| A. Checkout failing for 12% of requests for 15 minutes | 12 is at least 5 and under 50; 15 minutes is at least 5 | SEV2 | Top: all responders on it now |
| B. Expired sale banner, one-line fix | No function failing | SEV4 | High: fixed within the hour because customers are being misled and the fix costs minutes |
| C. Quarterly export fails for its 3 users | Non-core feature unavailable, workaround is to ask the data team for the file | SEV3 | Low: next sprint |
Notice that B has the lowest severity and a higher priority than C, which has a higher severity. A single combined "P1 to P4" number hides that, which is why teams that want clean on-call rules keep severity (a fact about impact, used to decide who is paged) separate from priority (a scheduling decision made by whoever owns the backlog).
Common mistakes
- Setting severity by who is shouting loudest or by how interesting the bug is, instead of by measured impact.
- Writing criteria with no numbers or time window, so every incident becomes an argument.
- Defining severity by cause ("database problem") or effort ("hard fix") instead of effect.
- Creating so many levels that nobody can tell neighbours apart; many teams settle on four or five.
- Using severity as a synonym for priority, then being unable to express "tiny impact but must fix today".
You are faced with three simultaneous incidents: (A) 5% degradation in checkout success globally, (B) a batch job behind schedule affecting reporting, (C) CI pipeline failing for many PRs. Prioritize these incidents and justify your decision based on blast radius, business impact, and recoverability. Outline immediate first steps for each.
Sample Answer
The idea in plain words
When several incidents land together, you do not rank them by how alarming they sound. You compare three things for each: blast radius (how many people or how much of the system the failure reaches), business impact (what it costs per hour, or what deadline it threatens), and recoverability (how well understood and reversible the fix is). Then you put the scarce resource, engineers, where one more person reduces the most harm. I would work (A) checkout first, run (C) the CI failure second, and give (B) the late batch job one engineer with a deadline check. The order flips if the fix for (A) needs the CI pipeline, because then (C) is on (A)'s critical path (the chain of steps that must happen before the fix can ship).
Assumptions (all hypothetical)
Revenue 2,000,000 USD per day, so 2,000,000/1,440≈1,389 USD per minute. 60 engineers use the CI pipeline (continuous integration, the automated build-and-test system that checks every code change), each loses 25% of working time while it is broken, loaded cost (salary plus overhead) 100 USD per engineer-hour. Six people are on shift: an incident commander (IC, who coordinates and decides) and five engineers. The IC does not debug.
Comparing the three
| (A) Checkout success down 5% globally | (B) Batch job late, reports delayed | (C) CI failing on many pull requests | |
|---|---|---|---|
| Blast radius | Every customer worldwide, but 1 in 20 checkouts | Internal analysts and report consumers | All 60 developers; also blocks deploys (CI failing on many pull requests, the proposed code changes waiting on checks and review) |
| Business impact | 2,000,000/24×0.05≈4,167 USD per hour (about 69.4 per minute) if failed shoppers do not return | Near zero until a deadline, then a cliff | 60×0.25×100=1,500 USD per working hour |
| Recoverability | Unknown cause; reversible if tied to a recent change | Usually rerun-able if the job is idempotent (safe to run twice) | Usually fast if it is infrastructure or a bad commit |
| Severity (impact only) | SEV2, rising to SEV1 at 10% | SEV3 | SEV3 |
| Response order | First | Staffed early, small | Second |
(A) loses about 4,167/1,500≈2.8 times as much per hour as (C), on the stated assumptions, counting both per hour of an incident open during working hours; outside working hours (A) keeps losing money while (C) loses almost nothing, so 2.8 is a floor. (A) also harms customers. That sets the order. Note the difference between severity and priority: (C) is low severity but its priority rises sharply if it blocks the fix for (A).
Allocating five engineers
- (A): three engineers and the IC: the checkout service owner, a payments or platform engineer and a site reliability engineer (SRE).
- (C): one engineer from the CI platform team.
- (B): one engineer from data engineering, time-boxed (given a fixed 15-minute limit) to establish the deadline and the rerun time, then they continue if needed.
- Reassess every 30 minutes. The reason not to put all five on (A): after the first few people, extra hands on one unknown cause add coordination cost faster than speed, while (B) and (C) each need only one person to progress.
Immediate first steps
(A) Checkout.
- Confirm with an independent signal (checkout success rate by dashboard, plus support contacts).
- Slice the 5% (split the failing checkouts by attribute) by region, platform, payment method, client version. A global 5% is often one payment method or one version failing completely.
- List changes in the last few hours (deploys, config, feature flags (switches that turn a feature on or off without a deploy), provider incidents).
- If a change correlates, roll back or turn the flag off first, diagnose second.
- Check the payment provider's status; if the provider is the cause, fail over (switch to a standby route) or reduce its traffic if a second route exists.
(B) Batch job.
- Find out who consumes the output and when it is needed: the deadline decides everything.
- Check the job's state: failed, stuck or just slow. Do not kill it blindly.
- Check whether a rerun is safe and how long it takes. Example: rerun takes 2 hours, deadline is in 3 hours, so the slack is 3−2=1 hour. The rerun must start within the hour.
- Look for contention (jobs competing for the same resources: was it starved of resources by (A)'s mitigation or by other jobs).
- Tell the consumers the expected time.
(C) CI.
- Look at the first failing step in a failing run: infrastructure (runner capacity, package or image registry, an expired credential) or code (a broken commit on the main branch).
- If it is a broken commit, revert it; if infrastructure, restore capacity or pin the last good version.
- Post one message to developers: what is broken, merge guidance, next update time.
- Confirm an emergency path exists to ship a rollback without the CI pipeline (a prebuilt artifact deployed with approval), in case (A) needs it.
Strategic customer SLA versus internal-only impact
An SLA (service level agreement) is the contractual promise to a customer, with a penalty if it is missed.
Put both in the same unit. Internal impact is priced in engineer-hours (as for (C)). An external commitment has a cliff: little cost until the deadline, then a fixed penalty plus relationship risk. Suppose (B) is the contractual daily report for a strategic customer paying 50,000 USD per month, with a 10% credit on a miss: 0.10×50,000=5,000 USD, equal to 5,000/4,167≈1.2 hours of (A)'s loss. The rule I use: compare time to the cliff with time to fix, and give a deadline-bound item the one engineer it needs before the deadline arrives rather than queueing it behind the larger incident. An SLA does not outrank (A) for the three engineers, but it does move (B) from "later" to "staffed now", and it raises (B)'s severity to SEV2.
What would flip the order
- (A)'s fix needs a deploy and the pipeline is the only path: (C) moves to first priority, with two engineers.
- (A) is a provider outage with nothing to do but wait: move engineers from (A) to (B) and (C).
- (A) rises to 10% or more: SEV1 and all hands.
Common mistakes
- Ranking by loudness: executives watch the checkout dashboard, the developers' channel is the loudest.
- Splitting every engineer across all three, which gives each a slow, shallow response.
- Forgetting dependencies between incidents.
- Treating "internal-only" as zero: 1,500 USD per working hour is real.
A page comes in for what looks like a serious customer-facing problem. Walk me through your first fifteen minutes: how you acknowledge, gauge scope, set a severity, decide whether to declare a major incident, and pull in the right people, and which decisions you deliberately defer.
Sample Answer
Direct answer
In the first fifteen minutes I do five things in order: acknowledge the page, measure scope from telemetry (not from the page text), set a provisional severity against a written table, decide whether to declare an incident, and pull in only the people the evidence calls for. I choose a mitigation (an action that stops or reduces the damage) before I understand the root cause, and I deliberately defer root cause, blame, the permanent fix and the final severity.
Terms: telemetry means metrics, logs and traces from the running system; severity is the impact level (SEV1 worst); the incident commander (IC) coordinates and decides without debugging; declaring an incident means formally opening the coordinated response: an IC, named roles, a status update on a fixed cadence and a written incident record. A major incident is the same thing as a declared incident here, so the declaring decision in the table is the major-incident decision the question asks about. What can come after it is a wider response (more teams, an executive briefing), which is a separate escalation step covered in the worked example. A mitigation is an action that stops or reduces the damage without fixing the root cause.
Three more terms used below: a rollback is returning to the previous known-good version of a deployment or configuration; a feature flag is a runtime switch that turns a feature on or off without a deploy; saturation means a resource (CPU, a queue, a connection pool) is full, so extra work waits or is rejected.
Assumptions for the worked example (stated, not real): a page arrives while a marketing campaign that is expected to roughly triple traffic is running, so one of the first questions is whether the campaign explains the alert. Normal traffic is 2,000 requests per second, the serving tier handles at most 5,000 requests per second, and the severity table is: SEV1 at least 50% of core-journey requests failing, SEV2 at least 5% and under 50%, SEV3 under 5%.
Minute by minute
| Minutes | Step | What I do and decide |
|---|---|---|
| 0 to 2 | Acknowledge | Acknowledge the page so the system stops escalating to others; open a working channel (a chat room for notes and findings, not yet a declared incident) and write "investigating, level not yet set" |
| 2 to 6 | Gauge scope | Check the four standard first-look signals (errors, latency, traffic, saturation) on the dashboards: error rate by journey (is the core journey affected?), latency (how long requests take), traffic (requests per second), and saturation (CPU, queue depth meaning the number of requests waiting, connection pools meaning the limited set of open database connections). A normal reading is the same signal at the same hour last week; the difference from that baseline is what matters. Then segment, which means splitting the numbers by region or customer group to see who is affected, and since when. Then ask "what changed": a deploy, a feature flag, a configuration change, or the campaign |
| 6 to 8 | Set severity | Apply the table to the measured numbers and write the level and the evidence in the channel. When two levels are plausible, choose the higher one and set a time to re-check |
| 8 to 10 | Decide whether to declare | Declare (add an IC, named roles, a status cadence and an incident record on top of the working channel opened at minute 0 to 2) when impact meets the table at SEV1 or SEV2, or when more than one team is needed, or when I cannot find an owner or a mitigation in the first ten minutes |
| 10 to 15 | Pull in people and start mitigation | Page the owning team for the failing component and an IC if I should not be IC; pick the first mitigation (below); ask the support lead to expect customer reports |
Worked example: is it load or a bug?
Offered traffic at triple the normal rate is
3×2,000=6,000 requests per secondIf the serving tier can handle 5,000 requests per second and the excess is rejected, the largest share that can be served is 5,000/6,000=5/6≈83.3%, so at least
1−65≈16.7%of requests fail. On the table that is at least 5% and under 50%: SEV2, provisional. The telemetry check that separates load from a bug is timing: do the errors begin when traffic crosses roughly 5,000 requests per second, and do CPU or queue depth saturate at that moment? Read the two possibilities side by side (illustrative readings for this scenario):
| Signal | Points to load (capacity) | Points to a bug or bad change |
|---|---|---|
| When errors start | When traffic crosses about 5,000 requests per second | Before traffic rose, or right after a deploy or flag change |
| Traffic | Well above the same hour last week, tracking the campaign | Near normal, about 2,000 requests per second |
| Saturation | CPU or queue depth at its ceiling at the moment errors start | No resource full |
| Error shape | Mostly rejections or timeouts, spread across all segments | Concentrated in one endpoint, region or customer group |
If the left column matches, the cause is capacity and the mitigation is to add capacity or shed low-value load. If the right column matches, look at the change list instead.
Chosen mitigation, in this order of preference: roll back a change that lines up with the start (a known state, fast); scale out the serving tier if saturated, which means adding more servers or instances so the same traffic is spread wider; shed or degrade load if scaling is slow, which means deliberately rejecting or switching off low-value work (for example, turn off a recommendations widget with its feature flag) so the core journey keeps working. I would not try to find the root cause of a rare error while 16.7% of requests are failing.
Declaration decision: yes. At SEV2 with the core journey affected, the table says declare, so at minute 8 to 10 I declare, name an IC and start the status cadence. Declaring is the decision the question asks about, and it adds structure, not extra people. I would widen the response (bring in additional teams, brief executives, add a communications lead) only if scale-out does not work within the first ten minutes or a second team turns out to be needed, because either would mean the fix is neither quick nor single-team.
Decisions I deliberately defer
- Root cause and who or what is to blame.
- The permanent fix, and any redesign.
- The final severity (it is provisional and re-checked on a timer).
- Customer-facing root-cause statements and the postmortem schedule.
- Cleanup work such as removing temporary mitigations.
- Whether to throttle or pause the campaign, unless saturation proves unfixable within minutes (that is a business decision, so I would ask, not decide alone).
Common mistakes
- Reading the page text instead of the dashboards.
- Debugging before mitigating when a rollback or scale-out was available.
- Declaring late because the severity feels like an accusation. Declaring is cheap; delay is not.
- Paging everyone, which starts a crowd, rather than the owner of the failing component.
- Spending the first fifteen minutes on communication drafts and none on stopping the damage.
Unlock Full Question Bank
Get access to all 8 Incident Severity Classification and Escalation interview questions and detailed answers.
Sign in to ContinueJoin thousands of developers preparing for their dream job.